Skip to main content Skip to footer

Road Closures and Construction Projects

Road Closures

Keep up-to-date on road closures and construction work on roads that are under the jurisdiction of the Municipality of North Perth through the Municipal 511 website.

Operations

Project Details

*All dates are to be confirmed and will be updated on the site once Contractors have finalized their schedules. 

Road Construction

  • The Asphalt Resurfacing Program is an annual program included in the Public Works Capital Budget involving pulverization, rebuilding and paving operations.

2025 projects will include:

  • Line 88 between Road 146 Wallaceville to Perth Road 140/Wellington County Rd 9
  • Road 176 between Perth Line 86 to Perth Road 178

 

 

 

Beginning May 7, 2025 and running for approximately 2 weeks, boulevard clean-up and restoration with topsoil and sod will be completed.  Final surface asphalt is projected to commence in early June.

PIC Information - January 4, 2024

PIC Information - January 11, 2024

Tree Information

Please be advised of the road closure on Barnett Street W between Nelson Ave S and Mitchell Road S starting May 5th tentatively running until June 27th. Access to the Listowel Carriage Shopping Centre, Walmart parking lot entrance, will be maintained from Nelson Ave S. The construction along Mitchell Rd S between Barnett St to Kincaid St will involve reduced lanes during this time. Please anticipate delays and plan accordingly.   

 

Through the Connecting Links Program, the Province of Ontario is investing in the construction and repair of roads and bridges on connecting links. Connecting links are municipal roads designated under the Public Transportation and Highway Improvement Act. The Ministry will provide up to 90 percent, to maximum of $3 million per road project, of eligible capital costs. The project involves the resurfacing of Highway 23 (Mitchell Road S) connecting link between Kincaid Street and the south limit, just south of Barnett Street. This work will include:

  • Resurfacing of the road with the installation of curbs and gutters.
  • New storm drainage infrastructure and sidewalks on the east side of the roadway from Kincaid Street W to Barnett Street.
  • Expansion of the existing two-way turning lane through the entire section from Kincaid Street to Barnett Street, with access to Twamley Street.

 

Project started mid June with Omega Contractors Inc. conducting the work. The project was substantially completed in August 2024, with final asphalt to be placed by July 2025. All inspection and engineering is being provided by GEI Consultants

Nelson Ave. N (Main St W. to Elma St W.)

Tentatively starting late May-early June, 2025, boulevard clean-up and restoration with topsoil and sod will be completed along with final surface asphalt being placed.

 

PIC Information Package 

York, Nelson, John - Letter 

The Municipality of North Perth is undertaking a Servicing Master Plan for stormwater, wastewater and water servicing in the communities of Listowel and Atwood. The Master Plan was initiated in late 2021, investigation and surveying of assets is continuing in the data gathering phase. Existing and future needs for infrastructure as the two communities will be understood through the project that is expected for completion in 2023. Upon completion, the Master Plan will serve as a strategic document, and identify infrastructure upgrades or expansions to support continued growth and address existing deficiencies. 

The Master Plan Process

The Servicing Master Plan is being conducted in accordance with the requirements of the Municipal Class Environmental Assessment (Class EA) document, dated October 2000, as amended in 2007, 2011 and 2015 under the Environmental Assessment Act. Master Plan studies incorporate Phases 1 & 2 of the Class EA process (identification of the problem or opportunity, and evaluation of alternative solutions) and also includes consultation with the general public, community stakeholders, government review agencies and Indigenous communities. The process has just been initiated. There will be additional opportunities for public comment and input as the process moves forward. 

Public Involvement

Public consultation is a key component of this study. Initial comments are welcome at this time. As a part of the consultation component of this project, a public information meeting will be held during the course of the study. Details regarding the public meeting will be provided in a future notice. Any comments collected will be maintained on file for use during the project and may be included in project documentation. With the exception of personal information, all comments will become part of the public records. 

For further information on this project, please contact the consulting engineers: B.M. Ross and Associates Ltd., 62 North Street, Goderich Ontario, N7A 2T4 (519) 524-2641 Attention: Kelly Vader, Environmental Planner, Email: kvader@bmross.net. For information from the municipality contact Matt Ropp, Manager of Operations at mropp@northperth.ca.

North Perth has been developing a long-term strategy to strengthen and support the transportation network within the community. The North Perth Transportation Master Plan (NPTMP) will provide a vision and policy framework for a complete transportation system that will meet travel demands to 2041 in a manner that is sustainable and compatible with future growth. The study will identify the Road Network Hierarchy, assess future needs including truck routing and active transportation corridors as well as recommend needed policy and comment on the phasing and costs of recommended solutions. The study will follow the requirements of the Municipal Class Environmental Assessment (an approved process under the Ontario Environmental Assessment Act) and align with the Municipality’s Corporate Strategic Plan, land use plans, and other policies. The need for a Truck Route was identified through the NPTMP and is now a separated project where the evaluation of alternatives and a recommendation on a preferred option is now part of this project.

  • Initial review and the first round of Consultation and findings have been conducted (completed)
  • Assessment and Development of alternatives are being finalized (in progress, Council has asked for a Bypass selection to be included in the NPTMP)
  • A final round of Consultation is being planned for June 2022 
  • A parallel Study on Traffic and Pedestrian usage and potential traffic calming on Wallace Avenue South was completed ad implemented in 2021. 
  • Final Presentations on the Truck Route Recommendations and the Transportation Master Plan are expected to be presented to Council in late 2022.

 Presentation Information:

North Perth TMP - FAQ - 2024

North Perth Transportation Master Plan 

North Perth Transportation Master Plan - Appendices 

The Municipality of North Perth is completing a preliminary design assessment of a proposed truck bypass around Listowel as identified in the Transportation Master Plan. This phase includes further evaluating route options, staging, required land, infrastructure needs, and cost estimates. A detailed report will be presented to council in the fall of 2025.

Construction will be conducted from mid September - early December. 

 

 

 

 

Construction to replace Bridge 075115 on Line 75 is scheduled to begin later this year (2025), following the completion of design and tendering phases. The project will involve detailed construction administration and inspections to ensure safety and quality. Temporary traffic disruptions are expected during construction, and the Municipality will provide updates to keep residents informed. This replacement will enhance infrastructure reliability and support safe travel for all users.

The Municipality has engaged a qualified engineer to assess the condition of the L-5 Listowel Conduit, including gabion basket walls, retaining walls, and the pedestrian bridge along the 420-meter structure. This assessment will determine the necessary repairs or upgrades to ensure infrastructure safety, longevity, and effective stormwater management. The findings will also help guide budgeting and planning efforts, reflecting the Municipality’s commitment to maintaining safe, sustainable infrastructure that protects public assets and serves the community’s long-term needs.

Phase 2 of the North East Development Lands focuses on expanding residential areas along with highway commercial and light industrial lots by installing critical infrastructure, including sanitary sewers, watermain, and stormwater management systems. A new roundabout will be constructed to enhance traffic flow and safety within the neighborhood. This phase also involves extensive roadworks and landscaping to improve connectivity, accessibility, and overall community aesthetics. Emphasizing sustainable growth, the development ensures reliable access to municipal services and green spaces while supporting diverse land uses to meet the needs of residents, businesses, and future growth.

York Ave. N (McDonald St E to the dead end)

Tentatively starting late May-early June 2025, boulevard clean-up and restoration with topsoil and sod will be completed along with final surface asphalt being placed.

PIC Information Package 

York, Nelson, John - Letter 

Facilities

Project Details

  • The demolition of building has been completed. After surveys and public consultation, a park development report was completed for this property. Council directed staff to prepare a fundraising plan for their consideration, to offset costs for this project. Work on the fundraising plan is ongoing.

  • Construction has began and is estimated to be completed by Fall 2024. 

Sign up to our Newsletter

Stay up to date on the Municipality's activities, events, programs and operations by subscribing to our eNewsletters.

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.